Adani Enterprises Limited (AEL) plans annual capital expenditure of ₹35,000–40,000 crore over the next two years, with airports, data centres and its polyvinyl chloride (PVC) manufacturing complex at Mundra expected to absorb the largest share. The investment programme will support infrastructure expansion and bring major projects into commercial operation.
Head of Finance Manan Vakharia outlined the spending outlook during the company’s earnings call on 28 October 2026. The plans come as AEL seeks greater earnings contributions from businesses developed over recent years, while continuing construction across its portfolio.
What is planned for the Mundra PVC complex?
AEL’s proposed PVC complex at Mundra, Gujarat, involves investment of approximately ₹26,000 crore and annual production capacity of one million tonnes.
Management said around 60% of project expenditure and construction had been completed. The first part of the complex is expected to be commissioned in financial year 2027–28. Alongside PVC, the development includes related chemicals and chlor-alkali operations.
Vakharia indicated that the plant would require a further six to nine months after commissioning to stabilise. This means the start of production and the achievement of steady operating performance will be separate milestones in the project’s development.
How are airports contributing to growth?
AEL’s airport portfolio comprises eight airports, including Navi Mumbai International Airport. Management said the network accounts for approximately 23% of India’s passenger traffic and 29% of its air cargo volumes.
The company’s results show airport cargo handling reached approximately 320,000 tonnes during July–September 2026, an increase of 11% year on year. First-half cargo volumes rose 9% to approximately 620,000 tonnes.
Airport earnings before interest, tax, depreciation and amortisation (EBITDA) increased 52% to ₹3,275 crore during April–September. However, the business reported a pre-tax loss of ₹484 crore, with the company identifying higher depreciation following the capitalisation of Navi Mumbai airport.
Arun Bansal, Chief Executive Officer of Adani Airport Holdings, said management expects Navi Mumbai to reach an annualised passenger run rate of 20 million by the end of financial year 2027–28. Domestic and international route expansion is expected to support that increase.
How quickly will data-centre capacity expand?
AdaniConneX added a 240-megawatt hyperscale order at Navi Mumbai during the September quarter, taking its cumulative contracted capacity above 1.2 gigawatts.
Operational capacity reached 94.6 megawatts after customer handovers of 10 megawatts in Noida and 19.2 megawatts in Pune.
Management expects operational capacity to reach 120–150 megawatts by March 2027 and approach 500 megawatts over the subsequent 12–18 months. The distinction between contracted and operational capacity remains significant: customer commitments cover projects that are still at different stages of construction and implementation.
What do the latest results show?
AEL reported consolidated total income of ₹71,569 crore for April–September 2026, up 62% year on year. EBITDA increased 56% to a record half-year figure of ₹11,958 crore.
Profit after tax attributable to owners nevertheless fell 92% to ₹332 crore. The results included a ₹2,644 crore exceptional charge for a settlement with the US Office of Foreign Assets Control, while the previous-year period benefited from an exceptional gain.
Manufacturing expansion also continued. Solar module production capacity reached 10 gigawatts, and construction progressed on an additional six-gigawatt solar cell line.
Management did not provide a specific EBITDA forecast for financial year 2026–27. Project commissioning, customer handovers and the subsequent increase in utilisation will determine how the planned investment translates into operating earnings.