Tirupur-based Eastman Exports Global Clothing plans to invest ₹266.2 crore in three garment manufacturing units in Andhra Pradesh’s Chittoor district, its first manufacturing expansion outside Tamil Nadu. The project will produce knitted and woven garments using technology to monitor and coordinate production. The first unit is scheduled to begin commercial production in April 2027. Officials estimate that the three units will support about 4,500 jobs, including more than 3,000 direct roles and around 1,500 indirect jobs.
Where will Eastman build its Chittoor garment units?
Eastman will start with a leased, 100,000-square-foot facility at Gandlakothur, where it plans to invest ₹25.8 crore. The other two units will be developed at Thenabanda village. The first Thenabanda unit involves an investment of ₹163.3 crore and is due to start commercial production in October 2028. The second, with an investment of ₹77.1 crore, is scheduled to follow in July 2029.
The phased rollout allows Eastman to start production at the leased facility more than a year before the first Thenabanda unit is due to open. The Chittoor location provides road access via National Highway 716 and keeps the new facilities connected to the company’s established supply base in Tirupur and Coimbatore.
What will the smart garment facility do?
The units will bring fabric cutting, stitching, printing, finishing and packing into an integrated production process. Eastman plans to use modern machinery and technology to coordinate these stages, improve precision and track production. Dyeing and other wet processing are outside the project’s scope, so the units will focus on garment assembly and finishing.
How does the investment fit Eastman’s export business?
Founded in 1983, Eastman operates 17 factories in Tamil Nadu, with more than 16,000 machines and a workforce of over 20,000. Its existing capacity is about eight million garments a month, and nearly 90 per cent of its output is exported. Its customers include Gap, Tommy Hilfiger, Nautica, Decathlon and Walmart. The available project details give no separate production capacity, export target or shipping gateway for the Chittoor units.
Why has Andhra Pradesh classified it as a mega project?
Of the ₹266.2 crore investment, ₹233.4 crore qualifies as eligible fixed capital investment. That exceeds the ₹200 crore threshold for mega projects under the Andhra Pradesh Textile, Apparel and Garments Policy 4.0 for 2024–29. The classification allows the state to consider project-specific incentives. The policy supports investment across textile and apparel manufacturing, including weaving, knitting and integrated units.
FAQs
When will Eastman’s first Andhra Pradesh garment unit start production?
Commercial production at the leased Gandlakothur facility is scheduled for April 2027. The two Thenabanda units are expected to follow in October 2028 and July 2029.
How many jobs could the Chittoor project create?
Officials estimate around 4,500 jobs, including more than 3,000 direct roles and about 1,500 indirect jobs.