The Cabinet Committee on Economic Affairs approved a second container terminal at Kamarajar Port in Tamil Nadu on 25 November 2026. The project will add annual capacity of 2 million twenty-foot equivalent units (TEUs) and give the port an 18-metre design draught to accommodate larger mainline ships. The government estimates the public-private partnership (PPP) component at ₹4,288.26 crore, including Goods and Services Tax (GST).
What will the new Kamarajar Port container terminal handle?
The terminal will occupy a 111-acre site and have a 900-metre-long quay, a berth width of 30 metres and a depth of 20 metres alongside. It is designed to handle container ships up to 400 metres long with a capacity of up to 24,346 TEUs.
The additional capacity is intended to serve containerised export and import cargo from the Chennai–Ennore industrial region and the wider southern hinterland. The government expects the deeper terminal to support more direct calls by large mainline vessels. For shippers, direct services could reduce reliance on feeder connections through overseas transhipment hubs and lower the associated costs.
Kamarajar Port handled 49.08 million tonnes of cargo and received 1,008 vessels in the 2025–26 financial year, including container throughput of about 700,000 TEUs. The government reported that the port’s overall cargo volume grew at a compound annual rate of 13.64 per cent over the preceding five years.
How will the project be financed and awarded?
The government proposes to select the private concessionaire through open global bidding. Under the design, build, finance, operate and transfer (DBFOT) model, the winning bidder will arrange financing, build and operate the terminal, and recover its investment through user charges governed by the concession agreement and applicable tariffs. The planned concession runs for 40 years.
The estimated private investment comprises ₹2,429.32 crore for the first phase and ₹1,858.94 crore for the second. Kamarajar Port Limited is expected to spend a further ₹450 crore on dredging. The project proposal calls for environmental and other necessary clearances to be obtained before the bid deadline.
When will the second terminal begin operations?
The first phase, with annual capacity of 1.1 million TEUs, is scheduled for completion within 24 months of the concession award. Commercial operations are due to start in month 25. Construction of the second phase, which adds capacity of 900,000 TEUs a year, is scheduled to run from month 25 through month 48. Full commercial operations are due to begin in month 49.
FAQs
How much container capacity will the second terminal add?
It will add 2 million TEUs a year when both phases are operational.
Does the ₹4,288.26 crore estimate include dredging?
The estimate covers the PPP component, including GST. Kamarajar Port Limited will bear the separately estimated ₹450 crore dredging cost.
When does the construction timetable start?
The timetable starts on the date the concession is awarded. The first phase is due to enter commercial service in month 25.