Mangaluru International Airport broke ground on an expansion of its passenger terminal on 11 November 2026, with the project expected to more than double annual capacity to 5.2 million passengers by the end of 2029. At Ahmedabad, Adani Airport Holdings is building a new integrated terminal that it expects to have ready for the October 2030 Commonwealth Games. The projects follow longer-term expansion proposals for the two airports that were estimated at a combined ₹23,200 crore in 2022.
What is being built at Mangaluru International Airport?
The project will add 27,100 square metres to the east side of the existing 48,574-square-metre terminal. It will expand check-in, security screening, immigration and baggage handling areas. The airport handled 2.55 million passengers in the 2025–26 financial year, above the existing terminal’s original design capacity of about two million. A separate proposed building would add parking for more than 800 vehicles and connect to the terminal by a pedestrian bridge.
The airport’s cargo terminal began domestic operations in May 2023 and international operations in July 2024. It handled 5,851 tonnes in 2025–26, up from 5,206 tonnes the previous year. International cargo accounted for 2,011 tonnes of the latest annual total, according to a consultation paper from the Airports Economic Regulatory Authority of India.
How is Ahmedabad expanding its terminal and air cargo facilities?
Adani Airport Holdings chief executive Arun Bansal told investors on 28 October that the new integrated passenger terminal at Sardar Vallabhbhai Patel International Airport would be ready for the 2030 Commonwealth Games. The airport operator says upgrades to its existing integrated cargo terminal since May 2025 have almost doubled that facility’s handling capacity. It also lists a new import cargo terminal, expanded domestic cargo facilities and an integrated courier terminal among its upcoming projects.
What did the original ₹23,200 crore proposals cover?
The 2022 proposals put Ahmedabad’s expansion at ₹18,000 crore and Mangaluru’s at ₹5,200 crore. Gujarat granted environmental clearance in November 2022 for Ahmedabad’s long-term expansion to 40.33 million passengers and one million tonnes of cargo a year. Karnataka granted environmental clearance in May 2023 for Mangaluru’s longer-term plan to handle up to 22.5 million passengers and 120,000 tonnes of cargo annually. The latest terminal updates give construction timelines for specific projects. They do not give a revised combined cost for the two airports’ long-term expansion plans.
FAQs
When will Mangaluru’s expanded terminal be ready?
The airport expects to complete the current expansion by the end of 2029, raising annual passenger handling capacity from about 2.5 million to 5.2 million.
How is Adani financing airport upgrades?
Adani Airport Holdings raised US$750 million from international banks in June 2025. The company earmarked US$400 million to refinance debt and the balance for expansion and other investments across six airports, including Ahmedabad and Mangaluru, as well as its non-aeronautical businesses.