National Aluminium Company Limited (NALCO) is evaluating sites in India for a new aluminium smelter capable of producing 500,000 tonnes a year, while advancing a separate expansion at its existing Angul plant in Odisha. Speaking in Bhubaneswar on 13 November 2026, Chairman and Managing Director Brijendra Pratap Singh ruled out relocating the Angul smelter to Andhra Pradesh. The company has yet to announce a site for the greenfield project.

Angul expansion would lift smelting capacity to nearly one million tonnes

NALCO puts the approved investment for its proposed Angul expansion at about ₹30,000 crore. The project would add 500,000 tonnes of annual smelting capacity to the existing 460,000 tonnes, taking the Odisha plant to about 960,000 tonnes a year. NALCO has signed a technology licensing agreement with Emirates Global Aluminium (EGA) for the expansion.

The Ministry of Mines cited December 2030 as the commissioning target. In a 3 November investor call, Singh described December 2030 as the target for mechanical completion and said commissioning could begin in the first quarter of 2031. He said the detailed project report could go to the board for approval by February 2027. A planned 1,080-megawatt captive thermal power plant, to be developed through an equal joint venture with NLC India Limited, would supply the expanded smelter.

Damanjodi refinery expansion could add alumina export cargo

The fifth production stream at NALCO’s Damanjodi refinery in Odisha would raise annual alumina capacity from 2.1 million tonnes to 3.1 million tonnes. The company expects the Pottangi bauxite mines to start operations within two to three months of the November briefing, taking its bauxite output from about seven million tonnes to more than 10 million tonnes. Bauxite is the raw material used to produce alumina, which is then smelted into aluminium.

NALCO expects the expanded refinery to produce more alumina than the Angul smelter will need, even after its capacity increases. The company plans to export the surplus initially. Its proposed greenfield smelter would provide a longer-term option to convert that alumina into aluminium in India.

Visakhapatnam Port handles NALCO’s bulk alumina exports

NALCO already moves alumina by rail from Damanjodi to Angul and to Visakhapatnam Port in Andhra Pradesh. At Visakhapatnam’s inner harbour, it operates three 25,000-tonne alumina storage silos and mechanised loading facilities with a peak loading rate of 2,200 tonnes an hour. The same facility handles imports of caustic soda for dispatch by rail to Damanjodi. This existing rail and port network gives the company an export route for surplus refinery output.

FAQs

Has NALCO confirmed a new aluminium smelter in Andhra Pradesh?

NALCO is evaluating suitable sites in India for a 500,000-tonne-a-year greenfield smelter. It has yet to announce a location. Singh separately ruled out moving the existing Angul plant to Andhra Pradesh.

How much alumina will Damanjodi be able to produce after expansion?

The fifth refinery stream is designed to raise annual capacity to 3.1 million tonnes from 2.1 million tonnes. NALCO plans to sell surplus alumina in export markets initially.

Facebook
Twitter
LinkedIn
WhatsApp
Email

SUBSCRIBE

One Ocean Maritime Media Private Limited
Join Our Newsletter
Email
Name
Share your views in comments

Leave a Reply

Your email address will not be published. Required fields are marked *