The Ministry of Railways spent approximately ₹2.15 lakh crore on capital expenditure during April–September 2026, utilising around 77% of the ₹2.81 lakh crore budget estimate used in the half-year comparison. This exceeded the Ministry of Road Transport and Highways’ utilisation rate of 58%, with railway investment continuing to focus on network expansion and capacity enhancement.
Highways capital expenditure stood at approximately ₹1.78 lakh crore against an annual budget estimate of ₹3.09 lakh crore. Railways therefore led both in expenditure and the proportion of its allocation utilised during the first half of financial year 2026–27.
How does spending compare with the previous year?
Railways’ utilisation increased from 69% in the corresponding period of FY2025–26 to around 77%, an improvement of approximately eight percentage points.
Across the Union government, capital expenditure rose to about ₹6.5 lakh crore from ₹5.8 lakh crore a year earlier. Reported utilisation of the annual capital expenditure budget increased to 53.1%, compared with 51.8%.
The railway and highways ministries together spent roughly ₹3.93 lakh crore, accounting for about three-fifths of the reported central capital expenditure total. The figures underline the importance of transport infrastructure in the government’s investment programme.
What is the broader railway investment plan?
The half-year utilisation comparison should be distinguished from Indian Railways’ broader annual capital expenditure programme. The government’s Budget announcement placed total planned railway capital expenditure for FY2026–27 at ₹2,93,030 crore.
The programme covers freight infrastructure, passenger connectivity, capacity expansion and safety. Nearly ₹1.20 lakh crore was earmarked for safety-related works, including track and rolling-stock maintenance, overhead electrical systems and deployment of the Kavach automatic train protection system.
Consequently, the spending total encompasses several categories of investment. It should not be read as expenditure exclusively on freight corridors or port connectivity.
Which projects are relevant to freight movement?
A major freight proposal in the Union Budget is the 2,052-km Dedicated Freight Corridor connecting Dankuni in West Bengal with Surat in Gujarat. The announced route passes through Odisha, Chhattisgarh, Madhya Pradesh and Maharashtra.
The corridor is intended to connect with the Western Dedicated Freight Corridor, creating an additional route for goods moving towards west-coast ports. The government has positioned it as a means of relieving congestion and strengthening east–west industrial connectivity.
This remains a proposed infrastructure development. Its inclusion in the investment agenda does not establish how much of the reported first-half expenditure was spent on the corridor.
How will additional tracks support bulk cargo?
Capacity expansion also includes projects on existing railway routes. On 9 September 2026, the Cabinet approved three multitracking projects with an estimated combined cost of ₹10,783 crore.
These cover a fourth line between Kharagpur and Jharsuguda’s Bagdehi section, a fourth line between Katni and Pendra Road, and a third line between Bilaspur’s Uslapur section and Pendra Road.
Together, they cover approximately 656 km across five states and are planned for completion by FY2029–30. The government estimates that the additional capacity could support 27 million tonnes of annual freight traffic, particularly coal, cement, iron and steel.
The projects illustrate the practical purpose of railway capacity investment: easing congested sections and improving service reliability for industrial cargo. Their expected benefits will depend on completion and commissioning, rather than budget utilisation alone.
For freight customers and port-linked supply chains, the distinction between expenditure and operational capacity remains important. The half-year figures indicate the pace of investment, while completed tracks, functioning terminals and reliable train services will determine the resulting logistics improvements.