Udupi Cochin Shipyard has launched the first of eight 6,300 DWT dry cargo vessels being built for Norway’s Wilson ASA, with delivery scheduled for December 2026. The Malpe yard also laid the keel for the third vessel and began steel cutting for the fourth, advancing several stages of the export programme.
Article
Largest vessel marks a step forward for Malpe
The UCSL cargo vessel launch on 26 October 2026 marked a significant production milestone for Udupi Cochin Shipyard Limited, a wholly owned subsidiary of Cochin Shipyard Limited.
The first vessel in Wilson ASA’s eight-ship, 6,300 DWT series entered the water at Malpe in Karnataka. At 99 metres long and 15.85 metres wide, it is the largest vessel built at the yard since operations resumed under Cochin Shipyard’s ownership.
Its cargo hold has a capacity of 316,278 cubic feet. Netherlands-based Conoship International designed the vessel, which is intended for general cargo operations in European coastal waters.
Wilson chairman Eivind Eidesvik and his daughter Anna Eidesvik jointly launched the ship. Norwegian Ambassador to India May-Elin Stener laid the keel for the third vessel, while Union Shipping Secretary Vijay Kumar participated by video link.
Construction progresses across the series
The launch took place alongside keel laying for the third ship and steel cutting for the fourth, demonstrating progress across successive vessels.
These milestones represent different stages of construction. Steel cutting begins fabrication, keel laying marks the start of hull assembly, and launching moves the vessel into the water ahead of remaining completion and acceptance work.
The first ship is scheduled for handover in December 2026. The launch therefore advances the programme towards delivery, while the vessel remains under construction.
For the yard, overlapping work on several sister vessels creates opportunities to apply production experience across the series. The commercial benefit will depend on maintaining quality, coordinating equipment installation and meeting contractual delivery requirements.
Repeat order followed smaller cargo ships
The larger vessels build on Wilson’s earlier relationship with UCSL.
In June 2023, the Norwegian operator ordered six 3,800 DWT dry cargo vessels. The first ship in that programme, Wilson Eco I, was delivered in April 2025, establishing an initial reference for the yard’s European export work.
The follow-on announcement in June 2024 covered four firm 6,300 DWT vessels and arrangements for four additional ships. Cochin Shipyard then indicated that the overall eight-vessel programme would be executed by September 2028.
A subsequent government announcement in April 2025 confirmed the eight-ship order at ₹1,041 crore. The progression from smaller vessels to a larger series illustrates the expanding scope of the customer relationship.
Diesel-electric design targets efficient operations
The 6,300 DWT vessels were ordered with diesel-electric propulsion for transporting general cargo in Europe’s coastal trades.
The design combines operational flexibility with an emphasis on fuel efficiency. Wilson’s newbuilding programme also provides for future integration of technologies such as wind-assisted propulsion, batteries and alternative fuels.
Those provisions describe design adaptability. They should be distinguished from equipment already installed or fuels approved for use on the newly launched vessel.
In its 2024 annual report, Wilson described the combined programme of six 3,800 DWT and eight 6,300 DWT ships as a means of increasing carrying capacity while improving environmental performance.
For a shortsea operator, vessel efficiency affects both operating expenditure and emissions. Repeat construction also allows shipbuilders and equipment suppliers to develop familiarity with the machinery, systems and production requirements of a common design.
Export programme builds on yard revival
Formerly Tebma Shipyards, the facility was acquired by Cochin Shipyard through the National Company Law Tribunal process in 2020 and restarted operations in 2021.
Its subsequent work has included aluminium hulls for the Kochi Water Metro, fishing vessels and harbour tugs, alongside Wilson’s cargo ships. This mix has supported the rebuilding of production activity across domestic and export contracts.
The latest launch adds a larger commercial vessel to that record. It also reinforces the role of Indian yards in supplying European shortsea fleets through partnerships involving overseas shipowners and designers.
The immediate priorities are completing the first vessel for its planned December handover and sustaining construction on the remaining ships. Delivery performance across the series will provide a stronger measure of execution than any single construction milestone.
FAQs
Who is the vessel being built for?
It is being built for Norway-based Wilson ASA as part of an eight-vessel programme.
What are its principal dimensions?
The launched vessel is 99 metres long and 15.85 metres wide, with a deadweight capacity of 6,300 tonnes.
When is delivery expected?
The first vessel is scheduled for delivery in December 2026.
What other milestones were completed?
UCSL laid the keel for the third vessel and began steel cutting for the fourth.
Who designed the vessels?
Conoship International of the Netherlands designed the series for European general cargo operations.