Welspun Corp has approved a US$115 million expansion at its Arkansas pipe plant and a Jordan manufacturing and coating project costing up to US$125 million with Perma-Pipe. The investments strengthen its overseas production footprint as large pipeline orders provide longer-term demand visibility.

Arkansas plant to add spiral-pipe capacity

The Welspun Corp expansion programme includes an additional helical submerged arc welded, or HSAW, pipe facility at Little Rock, Arkansas.

The US project will add 225,000 tonnes of annual capacity to the existing 350,000 tonnes, taking the total to 575,000 tonnes. The company expects the facility to become operational in March 2028 and plans to finance the investment through internal accruals.

The board approved the investment on 29 October, citing its orderbook and demand visibility for US oil and gas pipeline projects.

Jordan investment will be shared with Perma-Pipe

The board also approved a Jordan project involving total investment of up to US$125 million, to be funded approximately equally by Welspun and Perma-Pipe International Holdings.

The combined US and Jordan project budgets amount to US$240 million. However, the Jordan figure represents the total partnership investment, rather than expenditure to be borne entirely by Welspun.

The proposed facilities will manufacture and coat pipes ranging from 24 inches to 120 inches in diameter. Definitive agreements will establish detailed governance and operating arrangements.

Water infrastructure anchors regional plans

The Jordan development builds on a memorandum of understanding announced in September with Perma-Pipe, the developers of Jordan’s National Water Carrier Project and the Jordanian government.

The partnership combines Welspun’s large-diameter steel-pipe manufacturing capability with Perma-Pipe’s coating and engineered-piping expertise. Anti-corrosion systems are an important component of pipeline projects because they protect steel surfaces and support operating life.

The earlier agreement envisaged an integrated manufacturing and coating platform serving water, energy, oil and gas, and infrastructure projects in Jordan and neighbouring markets.

Its proposed regional role could extend to future reconstruction requirements in Syria, Lebanon, Iraq and Gaza. The partners also identified potential opportunities associated with regional energy infrastructure directed towards the Port of Aqaba.

Those opportunities describe the intended market reach of the platform. They should be distinguished from confirmed supply contracts or committed reconstruction orders.

Quarterly earnings increase alongside investment approvals

Welspun reported revenue from operations of ₹4,643.72 crore for the quarter ended 30 September 2026, an increase of approximately 6.2% year on year.

Profit attributable to owners rose to ₹498.56 crore from ₹439.68 crore, an increase of 13.4%. This is the owners’ share of earnings, which differs from total consolidated profit after accounting for non-controlling interests.

The results accompany investment decisions intended to expand manufacturing capability across several markets. The company also reported a global orderbook of approximately ₹50,000 crore, providing a substantial execution pipeline.

Large US orders provide the background

The Arkansas investment follows a series of significant US contract announcements.

In August 2026, Welspun disclosed an approximately US$1.8 billion pipe order, valued at around ₹17,200 crore, for supply from its US manufacturing facility.

The company described it as the largest single order in its history and scheduled execution across FY2028 and FY2029.

That delivery period gives useful context to the proposed March 2028 commissioning of additional capacity. However, the disclosures do not establish that the new facility is dedicated exclusively to this contract.

A further US$580 million order announced in October covers coated pipes for a natural-gas pipeline in the Permian Basin. The contract connects Welspun’s manufacturing business with continuing investment in US gas transmission infrastructure.

Manufacturing location shapes supply-chain strategy

The two overseas projects address different commercial requirements. Arkansas adds capacity within an established market, while Jordan provides a potential production base closer to regional infrastructure customers.

For heavy, large-diameter pipes, manufacturing location influences transport planning, handling requirements and delivery coordination. Combining production and coating can also reduce the number of movements between separate processing locations.

The immediate milestone is board approval. Commercial benefits will depend on completing the facilities, securing the necessary arrangements and converting the order pipeline into production, deliveries and cash flows.

FAQs

How much will the US expansion cost?

Welspun has approved investment of up to US$115 million.

When is the Arkansas facility expected to open?

The target is March 2028.

How much capacity will it add?

It will add 225,000 tonnes annually, raising US HSAW capacity to 575,000 tonnes.

Will Welspun fund the entire Jordan project?

No. The up-to-US$125 million investment will be shared approximately equally with Perma-Pipe.

What will the Jordan facilities produce?

They will manufacture and coat large-diameter pipes for water, energy and other infrastructure applications.

Facebook
Twitter
LinkedIn
WhatsApp
Email

SUBSCRIBE

One Ocean Maritime Media Private Limited
Join Our Newsletter
Email
Name
Share your views in comments

Leave a Reply

Your email address will not be published. Required fields are marked *